Malahat Corridor Study Timelines


 

The study, which is scheduled for completion in fall 2006, is being undertaken in two phases.

Phase 1
Summer 2005 to Spring 2006
Technical Analysis and Development of Options

  • complete analysis of travel demand, safety and operations, geotechnical, socio/economic, environmental and planning issues
  • determine medium and long-term goals and potential solutions
  • investigate a broad range of options

Phase 2
Spring 2006 to Fall 2006
Consultation and Evaluation of Options

  • gather input on the options
  • evaluate the options
  • recommend solution(s)
  • report on findings